Hydropower Stations |
|
|
Rehabilitated Stations |
|
|
Average Head (m) : 5.8 Discharge m3/s :15 Installed Capacity MW : 0.68 Annual Energy M.KWH: 4.75 number of units : 2 turbine type: Horizontal Frances Expected Emission Reductions (Ton/year Co2): 2600 |
|
| Small Naga Hamadi Hydro Statio Average Head (m) : 4 Discharge m3/s :150 Installed Capacity MW : 4.5 Annual Energy M.KWH: 38 number of units : 3 turbine type: Vertical Kaplan Expected Emission Reductions (Ton/year Co2): 21000 |
|